A new week in the adventure called Streetscape

The general contractor is hopeful this will be a week of progress in the project to re-make the four-block core commercial area in downtown Walhalla. Everyone passing through or in the vicinity of the work is asked to keep safety in mind.  On Main, from Tugaloo to College, Hutch ‘N Son is preparing for the re-construction of the block.  New curb and gutter should start Thursday, followed by new sidewalk. From College to Catherine, electrical conduit is planned for entire block.  All water line work has been finished.  One day this week the contractor plans a major cut at Main, at the College Street intersection.  That will allow electrical and AT&T conduits to go in on the north side of Main Street.