Work on Old St. John’s

April 16, 2013

Work on Old St. John’s Meeting House in Walhalla begins soon. Final plans for the rest rooms and electrical wiring have to be approved before bids are taken. The painting/finishing of the ceiling and walls will be accomplished by Linda Baldwin. Early next month, Mike Eldridge will build the front and rear porches. Moore Flooring will refinish the floors. Eldridge will complete the interior of the entryway. And materials for the pews will be purchased and built by the Hamilton Career Center carpentry classes.