Streetscape work has slowed down and there are now few traffic barrels.  The general contractor, Hutch ‘n Son, urges Walhallans to “enjoy your new downtown area while we try to finish the remaining work.”  The next step is the sensor installation in the pavement for the signal lights at the intersections.  Doing this work will be a sub-contractor from Columbia, but the general contractor says scheduling the sensor installations could take some time.  The final step of the entire project is to be the permanent striping.